Public Corporation “Kremenchug plant of technical carbon”

Design, production, supply, assembly and set up of power equipment at the enterprise:

  • repair and set up of SK-29-24 boiler st. # 3 (2003);
  • installation of amination of boilers’ feed water (2003);
  • Installation of two 2.5 MWt turbine generators in the boiler house # 3 (2004-2005).

The installed turbine generator supplies electricity to the plant using steam surplus of the plant’s boiler house # 2, which recovers the waste technological gas.

The turbine generator is mounted in the existing building of non-operating boiler house # 3 using the existing equipment’s piles foundation and the building structures.

Annual power generation by the turbine generator amounts to 20,000 MWt/h.